Being Successful as an Engineer

For better understanding it is useful to divide project control into three parts:
Scheduling.
Monitoring.
Controlling.
Scheduling is the planning and recording part of control. Let us use the project situation described in Chapter 3 to illustrate scheduling procedure.
First the project engineer with the help of his contributors lists the tasks to be accomplished. For our project we might note the following:
Establish initial overall concept.
Determine critical factors in each area.
Specify all interface conditions and alternatives.
Establish estimates for attainable recorder characteristics.
Establish final configuration and make recommendations.
Complete proposal document and costing.
Although these six items are reasonable here as the principal project tasks, and will serve nicely to illustrate control procedures, we would need more detail in our project story to know for certain what the list should be. For an actual development project or design project, scheduling will start in a great deal more detail. This kind of exploratory proposal work is relatively simple.
How much detail should you put into your schedule? That is an important question. If too little detail is included, planning has been insufficient to foresee major problems and consequent work needed. Then the project is not really scheduled at all. Schedules provided in that case are only a delusion.
Including too much detail, on the other hand, has two drawbacks. First, it obscures the really important tasks and milestones. More important than that, too much detail tends to make solution...