Power Plant Construction Management: A Survival Guide

Chapter 6: Setting Up the Jobsite

Overview

Once the contract negotiations are over and all parties have come to terms, both on technical issues and commercial conditions, it's usually time to get ready to start the job. The first step will be to set up the jobsite. It is here that attention to details will make the management of the project much easier. In fact, the whole purpose of the job setup is to facilitate the management process. Time should be spent thinking about all of the steps in the process of managing the project, before the actual labor efforts begin. Thought needs to be given to the administrative requirements, the actual site project management tools that will be used, the purchasing process, how quality will be measured and controlled, and how safety will be managed.

Often, only now is the site manager appointed. This manager may not know much about what transpired during the earlier phases of the project. The manager may be caught between trying to learn the details of the agreements made and trying to organize the site itself. Any help that can be provided will make this job much easier, and using the summary of the contract responsibilities, as described in the previous chapter, will help immensely as the manager goes about setting up the site.

Site Administration

With the details of the contract final and summarized, the process of setting up the actual site organization can start, and this means organizing the site administration. In order to ensure an orderly flow...

UNLIMITED FREE
ACCESS
TO THE WORLD'S BEST IDEAS

SUBMIT
Already a GlobalSpec user? Log in.

This is embarrasing...

An error occurred while processing the form. Please try again in a few minutes.

Customize Your GlobalSpec Experience

Category: Project Management Services
Finish!
Privacy Policy

This is embarrasing...

An error occurred while processing the form. Please try again in a few minutes.