Transmission and Distribution Electrical Engineering, Third Edition

The questions given in this section are designed to allow readers to familiarize themselves with standard Model Forms of Contract associated with design, supply and installation transmission and distribution project work. The questions are applicable to IMechE/IEE, MF/1, ICE and FIDIC Model Forms, copies of which will be needed to answer the questions. The relevant clauses should be quoted in the answers together with a summary and interpretation of these clauses.
The engineer (E) under a contract has appointed in writing an engineer s representative (R) with special powers. E is killed in an accident. R is aware of this but continues to issue instructions to the contractor.
Should the contractor follow these instructions if he is aware of E s death?
How should the situation be regularized?
A contractor issues a sub-contract for the supply of reinforcing rods for a substation concrete structure which houses plant which he is responsible for manufacturing and installing. Due to strike action in the sub-contractor s works, the main contractor is delayed for 28 days. He claims from the purchaser for a 28-day extension of time and associated costs. Advise the engineer on what action he should take.
A contractor who is in cash flow difficulties decides that he can ease his cash flow situation by delivering to site materials and plant well ahead of programme. His intention is to claim for the value of these materials in an interim payment certificate.
Will this scheme...