Maintenance Management: Its Auditing and Benchmarking: In Search of Maintenance Management Excellence

(This is an illustrative extract only; it is not the full list. Figures and Tables are given at the end)
A simple map of your plant showing the location of the maintenance trade groups. Also show the location of the stores and sub-stores (see Figure A2-1 for an example. The letters indicate the different trade groups, e.g., h indicates the power station mechanical group). Also provide an outline process flow diagram (see Figure A2-2 for an example).
Figure A2-1: Plant Layout
Figure A2-2: Alumina Refinery Process Flow Diagram
The location, composition, shift roster and function of each group using a list of the type shown in Table A2-1.
| Tradegroup | Location | Trade Mix | Shift Roster | Work Function |
|---|---|---|---|---|
| Raw materials mechanical (group i) | Wharf area workshop | 24 fitters | 6 fitters on a 4 7 shift roster | On Monday to Friday day shift, material handling equipment second line work. |
| On all other shifts plant wide first line work, other than where there is local cover. | ||||
| Raw materials electrical (group n) | Wharf area workshop | 3 electricians | Days | Material handling equipment, first and second line work. |
| Boiler house mechanical (group h) | Boiler house mechanical workshop | 18 fitters | 6 fitters on a 3 5 shift roster | First and second line cover for boiler house Monday to Friday. |
An outline of the structure of your administration, from Chief Executive downwards, using a diagram...