What are the key roles in an Enterprise SPMO?
These roles are defined as the Executive Stakeholder, Project Sponsor, Program Manager, Project Manager, Project Coordinator, Project Resources, and Business Systems Analysts.
Describe the major service areas of an SPMO.
They are Performance Reporting, Financial, Vendor, Issue, Quality, Change, and Risk Management.
What are several benefits of project performance reporting?
Benefits of performance reporting include providing a means to ensure the project makes orderly progress toward key milestones by charting progress metrics. They tie performance reports and project financials together for a consolidated picture of the overall status of a project.
List the five key components of project performance reporting.
Establishing program standards
Requesting and collect data
Consolidating information
Reporting development and continuous improvement
Reporting communications
Cite five to seven elements a project performance report should include.
Some examples of possible elements contained in a project performance report include:
Scope of deliverables: Planned, actual, and projected
Cost: Planned, actual, earned, and estimated at completion
Schedule: Planned, actual, and estimated
Quality: Planned, actual, and projected achievement
Risk: Planned, actual, and projected reduction
Benefits: Planned and achieved
Issues: Defined, corrective actions, status, management actions required
Why is financial management important in an enterprise SPMO environment?
Benefits of financial management include being able to explicitly define the financial controls and processes for the project and forecast project costs. It allows the team to improve estimates with consistent financial factors and to identify potential overruns and shortfalls in spending. It enables...