EC&M's Electrical Calculations Handbook

The labor units provided in the preceding figures include the following approximate amounts of work:
Actual installation: 69 percent
Nonproductive labor: 2.5 percent
Studying plans: 2.5 percent
Material procurement: 2.5 percent
Receiving and storage: 2.0 percent
Mobilization: 5.0 percent
Layout: 5.0 percent
Cleanup: 2.0 percent
Punch-list work: 5.0 percent
Coffee breaks: 3.5 percent
If one or more of the preceding categories of work will not be a part of the work scope of a given installation, then the total personnel-hour budget can be adjusted accordingly.
When a building is more than one floor in height, then the overall personnel hours for the project should be increased by 1 percent per floor.
When installing large conduit in parallel runs, less labor is required than for installing individual runs. Besides the labor column differences in the personnel-hour tables, the following further adjustments should be made to the conduit labor:
For two parallel conduits, deduct 10 percent of the conduit labor.
Staging of material at an electrical construction site is part of the manhour requirement for the project.
For three parallel conduits, deduct 15 percent of the conduit labor.
For four parallel conduits, deduct 20 percent of the conduit labor.
For five parallel conduits, deduct 25 percent of the conduit labor.
For over five parallel conduits, deduct 30 percent of the conduit labor.
When installing multiple conductors in a common conduit or in parallel conduit runs, less labor is required than for installing individual conductor pulls. Therefore, in addition...