Project Planning & Scheduling Using Primavera Contractor Version 4.1: For the Construction Industry

The next phase of a schedule is to add logic to the activities. There are two types of logic:
Relationships ( Dependencies or Logic or Links between activities), and
Imposed Constraints to activity start or finish dates. These are covered in the CONSTRAINTS chapter.
Primavera Contractor s Help file and other text use the terms Relationships and Logic for Relationships but does not use the terms Dependencies or Links.
We will look at the following techniques in this chapter:
| Topic | Notes for creating a SF Relationship |
|---|---|
| Drag the |
| Predecessor and Successors may be added and deleted from the Relationships, Successors or Predecessors tabs. |
| Double-click on an activity link in the Bar Chart or PERT view, the curser will turn appear as an |
|
|
| Double clicking in the Predecessor or Successor cells will open the Assign Predecessor form and the Assign Successor form. |
| Select the activities in... |