Project Planning & Scheduling Using Primavera Contractor Version 4.1: For the Construction Industry

A Resource has two principal components after it has been assigned to an Activity:
Quantity, in terms of Work in hours or Material quantities required to complete the activity, which are referred to as Units by Primavera Contractor, and
Cost, which is calculated from the Resource Unit Rate x Quantity. The Resource Unit Rate is termed Price/Unit in Primavera Contractor.
Each Resource and Expense has the same four fields for Costs and Units: Budget, Remaining, Actual and At Completion. The relationship among these fields changes depending on whether the activity is Not Started, In-Progress or Complete.
When an activity is Not Started and the % Complete is zero then:
Budget may be linked to Remaining and At Completion and therefore a change to one will change the other two and they will always be equal, and
Actual will be zero.
When the activity is marked Started and would normally be In-Progress and the % Complete is between 1% and 99% then:
Budget becomes unlinked from Remaining and At Completion, thus allowing progress and the At Completion value to be compared to the Budget, and
At Completion = Actual + Remaining and have a link to % Complete and a change in value to one will result in a change to other values.
When the...