Project Planning and Control Using Primavera Contractor Version 6: Including Versions 4.1, 5.0 and 6.1

The next phase of a schedule is to add logic to the activities. There are two types of logic:
Relationships ( Dependencies or Logic or Links between activities), and
Imposed Constraints to activity start or finish dates. These are covered in the Constraints chapter.
The Primavera Contractor Help file and other text use the terms Relationships, Links and Logic for Relationships but does not use the term Dependencies.
We will look at the following techniques in this chapter:
| Topic | Notes for creating a SF Relationship |
|---|---|
| Drag the |
| Predecessor and Successors may be added and deleted from the Relationships, Predecessor or Successor tabs. |
| Double-click an activity link in the Bar Chart or PERT view. |
|
|
| Double clicking in the Predecessor or Successor cells will open the Assign Predecessor form and the Assign Successor form. |
| Select the activities in the order they are to be linked, right-click and select Link Activities |