The Architect's Portable Handbook: First-Step Rules of Thumb for Building Design, Third Edition

Estimate Scheduling
| Project value | Const, time |
|---|---|
| Under $1,400,000 | 10 months |
| Up to $3,800,000 | 15 months |
| Up to $19,000,000 | 21 months |
| Over $19,000,000 | 28 months |
Design time runs 25 to 40% of construction time (up to 100% for small projects, including government review).
Construction time can be affected by building type. Using commercial buildings as a base, modify other building types: industrial: ?20%; research and development: +20%; institutional buildings: +30%.
Site Observation Visits
Take:
Plans
Specifications
Project files
Tape
Chalk
Camera
Paper
Pencil
Calculator
Checklist
Field report forms
Flashlight
String line and level
List of site visits for small projects:
After building stake out is complete
After excavation is complete and rebar is in place
When foundation is being placed
When under-slab utilities and stem walls under way
During placement of concrete slab on grade
During masonry and/or frame walls and columns and layout of interior walls
During floor and/or roof framing, wall and roof sheathing (prior to roofing)
During roofing
During drywall, plaster, plumbing, electrical, and HVAC
At end of project (punch list)