Planning & Scheduling Using Primavera Version 5.0 for Engineering & Construction: Planning and Progressing a Single Project Schedule With and Without Resources In An Established Project Environment

The finish date (and time) of an activity is calculated from the start date (and time) plus the duration over the calendar associated with the activity. Therefore, a five-day duration activity that starts at the start of the workday on a Wednesday, and is associated with a five-day workweek calendar (with Saturday and Sunday as non-work days) will finish at the end of the workday on the following Tuesday.
Primavera Version 5.0 has three categories for calendars:
Global These calendars are available to all Projects and Resources.
Project These calendars are only available to the projects they are created for and may only be created for a project when that project is open.
Resource A Resource calendar may be assigned to one or more Resources, which in turn may be assigned to an activity in any project. A Resource will be scheduled according to a Resource Calendar when the Activity Type is set to Resource Dependent, otherwise the activity is scheduled according to the Activity Calendar.
You may create a new or edit an existing Calendar to reflect your project requirements, such as adding holidays or additional workdays or adjusting work times. For example, some activities may have a 5-day per week calendar and some may have a 7-day per week calendar.
This chapter will cover the following topics:
| Topic | Menu Command |
|---|---|
| This calendar is assigned to new activities. From the Projects |