18.1: Understanding Resource Calculations and Terminology

18.1 Understanding Resource Calculations and Terminology

A Resource has two principal components after it has been assigned to an Activity:

  • Quantity, in terms of Work in hours or Material quantities required to complete the activity, which are referred to as Units by Primavera Version 5.0, and

  • Cost, which is calculated from the Resource Unit Rate Quantity. The Resource Unit Rate is termed Price/Unit in Primavera Version 5.0.

Each Resource and Expense has the same four fields for Costs and Units: Budget, Remaining, Actual and At Completion. The relationship among these fields changes depending on whether the activity is Not Started, In-Progress or Complete.

  • When an activity is Not Started and the % Complete is zero then:

    • Budget may be linked to Remaining and At Completion and therefore a change to one will change the other two and they will always be equal, and

    • Actual will be zero.

  • When the activity is marked Started and would normally be In-Progress and the % Complete is between 1% and 99% then:

    • Budget becomes unlinked from Remaining and At Completion, thus allowing progress and the At Completion value to be compared to the Budget, and

    • At Completion = Actual + Remaining and have a link to % Complete and a change value to one will result in a change to other values.

  • When the activity...

UNLIMITED FREE
ACCESS
TO THE WORLD'S BEST IDEAS

SUBMIT
Already a GlobalSpec user? Log in.

This is embarrasing...

An error occurred while processing the form. Please try again in a few minutes.

Customize Your GlobalSpec Experience

Category: Project Management Services
Finish!
Privacy Policy

This is embarrasing...

An error occurred while processing the form. Please try again in a few minutes.