Planning Using Primavera SureTrak Project Manager Version 3.0 Revised 2006

The end date of an activity is calculated from the start date plus the duration over the calendar associated with the activity. Therefore, a five day duration activity that starts on a Wednesday, and is associated with a five day work week calendar (with Saturday and Sunday as non-work days) will finish on the following Tuesday:
Every SureTrak schedule is created with a Global Calendar and a one Base (activity) calendar, Calendar 1.
Global Calendars
The Global Calendar may be edited for each new schedule.
The Global Calendar sets the default working days and hours used in new calendars and the holidays for all calendars.
The Global Calendar may not be assigned to an activity.
Base (activity) Calendars
Up to 31 Base calendars may be created and assigned to activities.
Base calendars are assigned to activities so as to allow for each activity s individual calendar requirements. For example, office work would be allocated a five-day calendar, while site work would be allocated a six-day calendar.
Templates should be created for projects that utilize the same calendars and this saves time when creating a new project.
Each Holiday or Non-workday nominated in the Global Calendar is reflected in all Base calendars. As a general rule you should make the Global Calendar 5 or 6 days per week at 8 hrs per day and include Public Holidays. Public Holidays on the same date every year may be made Annual. Rostered Days Off may...