Planning Using Primavera: Suretrak Project Manager Version 3.0

9.5: Constraints

9.5 Constraints

Constraints are used to impose logic on activities that may not be realistically scheduled with logic links. We will deal in detail with four constraints:

  • Start constraint Early

  • Finish constraint Late

  • Expected Finish

  • Float constraint As late as possible.

These are the minimum number of constraints that required to effectively schedule your project.

Start constraint Early (also known as start no earlier than" constraint) is used when the start date of an activity is known or known approximately. SureTrak will not allow the activity s early start prior to this date.

Finish Constraint Late (also known as finish no later" constraint) is used when the latest finish date is stipulated. SureTrak will not allow the activity s late finish after this date.

Expected Finish is used to calculate the remaining duration. SureTrak will calculate the remaining duration as the number of working days left between the start date (data date if in progress) and the nominated expected finish.

Float constraint As late as possible (also known as zero free float") is used to make the activity early finish immediately prior to its successors. A classical example is the just in time" delivery of materials before installation.

The other constraints are:

  • Start constraint Late Start no later than

  • Finish constraint Early Finish no earlier than

  • Start on Start no earlier than and Start no later than

  • Mandatory Start/Finish...

UNLIMITED FREE
ACCESS
TO THE WORLD'S BEST IDEAS

SUBMIT
Already a GlobalSpec user? Log in.

This is embarrasing...

An error occurred while processing the form. Please try again in a few minutes.

Customize Your GlobalSpec Experience

Category: Prototyping Services
Finish!
Privacy Policy

This is embarrasing...

An error occurred while processing the form. Please try again in a few minutes.