Planning Using Primavera Project Planner P3 Version 3.1 Revised 2006

Activity dates, remaining duration and percentage complete may be statused using one of three principal methods:
Using the Activity Form, (as outlined in the TRACKING PROGRESS chapter)
Using Columns
Recording Progress on the bar chart
Using Progress Spotlight & Update Progress.
The Activity Form may be used for statusing activities in conjunction with the Dates form for Suspending and Resuming activities.

A layout may be created with the columns required to status a project. You should display all the columns you wish to status.
Actual Start and Actual Finish columns are available in P3, see below.