19.4: Updating Dates and Percentage Complete

19.4 Updating Dates and Percentage Complete

Activity dates, remaining duration and percentage complete may be statused using one of three principal methods:

  • Using the Activity Form, (as outlined in the TRACKING PROGRESS chapter)

  • Using Columns

  • Recording Progress on the bar chart

  • Using Progress Spotlight & Update Progress.

19.4.1 Recording Progress Using Activity Form

The Activity Form may be used for statusing activities in conjunction with the Dates form for Suspending and Resuming activities.

19.4.2 Recording Progress Using Activity Columns

A layout may be created with the columns required to status a project. You should display all the columns you wish to status.

Actual Start and Actual Finish columns are available in P3, see below.

UNLIMITED FREE
ACCESS
TO THE WORLD'S BEST IDEAS

SUBMIT
Already a GlobalSpec user? Log in.

This is embarrasing...

An error occurred while processing the form. Please try again in a few minutes.

Customize Your GlobalSpec Experience

Category: Columns
Finish!
Privacy Policy

This is embarrasing...

An error occurred while processing the form. Please try again in a few minutes.