19.9: Updating Resources Using Resource and Costs Forms

19.9 Updating Resources Using Resource and Costs Forms

Select the Resources and or Costs forms to update the Resource Information.

  • The above example has the cost and quantities for Actual to date and To complete entered separately.

  • Percent expended is calculated as Actual to Date / Budget and expressed as a percentage.

  • Earned value is the Budget x Resource Percent complete To complete.

  • At completion is Actual to date + Cost to complete.

  • Variance is the difference between Budget and At completion.

UNLIMITED FREE
ACCESS
TO THE WORLD'S BEST IDEAS

SUBMIT
Already a GlobalSpec user? Log in.

This is embarrasing...

An error occurred while processing the form. Please try again in a few minutes.

Customize Your GlobalSpec Experience

Category: Project Management Services
Finish!
Privacy Policy

This is embarrasing...

An error occurred while processing the form. Please try again in a few minutes.