Planning Using Primavera Project Planner P3 Version 3.1 Revised 2006

To enter any resource data in a column you must Group by Resource and then costs and quantities may be updated using the columns.

The layout must be organized by Resource to allow resource column data to be edited.
Important The option to organize by Activity ID and then by Resource is available in SureTrak but not in P3. This makes finding activities difficult in large P3 schedules when organized by resource.